| Route |
Route details |
Project status |
Comments |
| 1 |
Bristol City centre to Parkway station |
Construction started 12th October |
Substantial completion March 2010 |
| 2 |
Parkway station to Cribbs Causeway |
Design and consult in 2010/11 |
Section between Parkway Station and Gipsy Patch Lane (B4057) |
| 3 |
Parkway station to Bradley Stoke |
Safety Audit completed. Notices prepared for raised crossing points |
Construction scheduled to start in February 2010 |
| 4 |
Bradley Stoke to Cribbs Causeway |
Safety Audit completed. Notices prepared for raised crossing points |
Construction scheduled to start in March 2010 |
| 5 |
Henbury to Cribbs Causeway |
Programmed for 2010/11 |
Design route and investigate land issues |
| 6 |
Bradley Stoke to Cribbs Causeway via Northfield |
Programmed for 2010/11 |
Design and consult on section to the east of the A38 |
| 7 |
Ring Road path |
Preliminary design subject to scrutiny in December 2009. Consultation started January 2010 |
Construction scheduled for Spring / Summer 2010 |
| 8 |
Emersons Green links to village centre |
Safety Audit completed. Notices prepared for raised crossing points |
Construction scheduled to start in February 2010 |
| 9 |
Northern Link to University of West of England |
Construction started 5th November 2009 |
Substantial completion by February 2010. Consult on northern extension to Winterbourne Road (B4057) during 2010/11) |
| 10 |
Southern Link to University of West of England |
Preliminary designs being worked up & cycle ride over route planned for February 2010 |
Consultation planned for Spring 2010 |
| 11 |
Western Link to University of West of England |
Design to be incorporated into Route 10 (above) |
Consultation planned for Spring 2010 |
| 12 |
Eastern Link to University of West of England |
Construction started 5th October 2009 |
Substantial completion by March 2010 |
| 13 |
Parkway station to Patchway via Filton |
Programmed for 2010/11 |
Design and consult on route either side of the Northfield development |
| 14 |
Emersons Green Science Park link |
Developer funded route |
|
| 15 |
Yate to Mangotsfield |
Initial landowner negotiations and consultation completed. Design work on-going – topographical and ecological surveys carried out |
Submission of planning application delayed until March 2010 due to transfer of land ownership. Route alignment of southern section being developed |
| 17 |
A38 road review |
Public consultation and Safety Audit completed |
Construction programmed for early 2010/11 |
| 18/19 |
A432/A4174 cycle review |
Public consultation and Safety Audit completed |
Construction programmed for early 2010/11 |
| Route signage |
All routes |
Consultation period ended October 2009 |
Posts for signs being ordered in February 2010. GIS / mapping work underway |
| Cycle parking |
|
External consultant has now submitted report listing potential cycle parking sites |
Contractor continuing with installations started in December 2009. Land owners being contacted where necessary. |